Pagladia Project
Dholla Hatighuli Project

3

Harang DDS

4

FMP

PROTECTION OF MAJULI ISLAND FROM FLOOD & EROSION  
  

INTRODUCTION  : 

 

Majuli, the largest inhabited river island in the world, is situated in the upper reaches of the river Brahmaputra between chainage 435 km and 520 km from Indo-Bangladesh border. The Island extends for a length of about 80 km in East-West direction and about 10 km to 15 km in North-South direction. It lies between latitudes 26o 45N  and   27 o 10N and longitudes between 93 o 40E and 94 o 35 E.

 

An administrative Sub-Division of Jorhat district, the Majuli Island represents a colourful rainbow of cultural integration with 70% of its population belonging to tribal communities such as Mishing, Deori, Kachari and Koch Rajbongshi. It has a population of 1.534 lakh as per 2001 census.

 

Majuli Island has been threatened by massive erosion since early 1950, as a consequence of dramatic morphological changes of the Brahmaputra River related to the two major earthquakes in 1947 and 1950. A study on erosion of Majuli Island shows that for the period 1914 to 2008 (94 years) there was a loss of about 227.43 sq.km area.

 

In order to bring the problem under control, the Govt. of Assam requested Brahmaputra Board for taking up protection work of Majuli Island. Accordingly, Brahmaputra Board agreed to take up the work and prepared a Detailed Project Report for protection of Majuli Island from the flood and erosion based on the recommendation of Master Plan and submitted the same to the CWC in August, 2000. The CWC cleared the schemes in August, 2003 for an amount of Rs. 86.56 crores. The project emphasized implementation of protection work in 3(three) phases such as Phase-1, Phase-II and Phase-III. Accordingly, Brahmaputra Board took up the following measures to arrest flood and erosion for protection of Majuli Island.

 

1.                  IMMEDIATE MEASURES  -

 

            Considering the time taken in the process of mandatory investment clearance for the DPR,  Brahmaputra Board took up immediate measures as per recommendation of the Expert Team. These works were started in January, 2004 and completed in February, 2005 at a cost of Rs. 5.92 crores.

 

 

Following are the main works carried out under Immediate Measures –

a)      Closing of 20 Nos of breaches on Malual-Malapindha dyke and PWD road.

b)      Raising and strengthening of 5.55 km embankment from Kamalabarighat to Kharkharijan.

c)      Construction of RCC porcupines permeable screens/spur/dampeners at various locations.

 

  1. PHASE-I WORKS  - 

The works under Phase-I was originally sanctioned for Rs. 41.28 crores in January, 2005 which was later revised to Rs. 56.07 crores. Phase-I work was started in March, 2005 and completed in April,2011. The total cost was incurred under Phase-I is Rs.53.34 crores upto April, 2011. Following are the main works carried out in Phase-I.

i)                    Raising and strengthening of the embankment system for a length of 90.08 km.

ii)                   Closing of breaches on PGJH road cum embankment.

iii)                 Anti erosion measures in the form of RCC porcupine screens, spur and dampeners in the affected areas.

iv)                 Construction and repair of nose portion of two land spurs at Sonowarkachari and Kandulimari.

 

  1.   EMERGENT WORKS  - 

      There was a devastating flood in the year 2007 which caused several erosion at various locations of Majuli. Standing Committee of Experts on Majuli which visited the erosion area in the year 2008 recommended a few measures to be completed prior to the monsoon of 2008. The works were started in April, 2008 and completed in September, 2008 at a cost of Rs. 4.62 crores. The works under emergent measures comprises of construction of RCC porcupines screens/dampeners at Bessamora, Dakhinpath, Bhogpur, Bengena-ati, Kamalabari, Bhakatchapuri and Pakhimuri reach.

 

  1. THE WORKS UNDER PHASE-II AND III  - 

Phase-II & III works envisages taking up permanent protection works like construction of boulder spurs in Majuli in addition to other measures. The works under Phase-II & III were started in March, 2009 and is targeted to be completed by March, 2012. The progress of work upto May, 2011 is 23.32% at a cost of Rs. 26.79 crores.

   
   
 
 
 
Copyright © 2003, Brahmaputra Board, Guwahati, Assam
Hosted by National Informatics Centre