Construction of Raised Plaforms

 

Status of Raised Platforms as on 31-07-2019

Sl No.
Name of Scheme
Qnty
District
Completed on
Honded over on
1 Bejartari
1
Kamrup (Rural)
March,2010
06.06.2011
2 Salmarapam (Toptola)
1
Morigaon
09-04-2011
20.05.2012
3 Garapar
1
Morigaon
09-04-2011
20.05.2012
4 Kapahtoli -2
1
Tinsukia
December
Under Process
5 Matmora
1
Dhemaji
March, 2007
Under Process
6 Kharubhuj
1
Goalpara
April, 2007
July,2007
7 Along L/B of Brahmaputra from Guimara to Nahira
3
Kamrup (Rural)
March, 2003
March,2010
8 Ulubari
1
Morigaon
03-11-2006
20.03.2008
9 Salekpathalighat
1
Majuli
July, 2011
May,2012
10 Jiakur
1
Kamrup
March, 2013
09.04.2013
11 Tulsimukh Kochgaon
1
Nagaon
29-04-2014
Under Process
12 Atoichuk
1
Majuli
July, 2013
September,2013
13 Dakhinpat
1
Majuli
September, 2013
September,2013
14 Kharkharijan
1
Majuli
July, 2013
September,2013
15 Ratanpur Miri
1
Majuli
August, 2014
November,2014
16 Barbalachar
1
Dhubri
November, 2014
20.09.2016
17 Satrakanara (Under execution)
1
Barpeta
May, 2018
29.06.2018
Total
19      

Construction of Raised Platform

On request from State Government of Assam, Brahmaputra Board has completed construction of 19 raised platforms at different locations to facilitate logistic support during flood for hunans and livestocks. Another raised platform at Satrakanara area in Barpeta District, Assam in under execution.During 2017-18, 55% of progress was achieved in execution of the raised platform with overall 91.24% progress up to Mach 2018.

In the report of performance evaluation study carried out through an independent agency, it has been advocated to construct more raised platforms for shelterof marooned people during floods. As per decision of 65th meeting of Brahmaputra Board, NDMA was requested to keep the Brahmaputra Board in the loop for assisting NDMA for implementation of such schemes in North Eastern Region.